    • Post-welding heat treatment process of equipment hatch for CAP1400 nuclear power plant

    • YU Jie

      123 ,

      DONG Yongzhi

      123
    • Vol. 49, Issue 4, Pages: 352-356(2019)   

    Scan for full text

  • Quote

    PDF

  • YU Jie, DONG Yongzhi. Post-welding heat treatment process of equipment hatch for CAP1400 nuclear power plant. [J]. 49(4):352-356(2019) DOI:
    Sections

    Abstract

    With its large structure size(the outer diameter of inserted plate is 8.5 m),narrow interval(595~620 ℃) of the post-welding heat treatment(PWHT),and major difference of plate thickness(the thickness of dome head is 36 mm,the thickness of insert plate,penetration sleeve as well as flange are all 130 mm),the PWHT process for equipment hatch is a big challenge. In this paper,the temperature uniformity of heat treatment furnace is measured to establish an effective heating area,which guarantees the precision range of heat treatment temperature. In this area,PWHT tests for module of dome head and flange and module of insert plate and penetration sleeves are carried out in furnace. The analysis results of tests procedure and heat treatment curves provide theoretical and data support for CAP1400 large penetration assembly PWHT.

    transl
    EN

    Keywords

    CAP1400; PWHT; equipment hatch; temperature uniformity

    transl
    EN

    Alert me when the article has been cited
    Submit

    Related Articles

    No data

    Related Author

    No data

    Related Institution

    Shanghai Nuclear Engineering Research & Design Institute
    China Nuclear Industry Fifth Construction Co.,Ltd
    Yantai Nuclear Equipment Engineering Technology and Research Center
    Shandong Nuclear Power Equipment Manufacturing Company
    0