VVER-1000核电机组主管道焊接施工工艺优化
Optimization of the welding Construction Process for the Main Pipeline of VVER-1000 Nuclear Power Unit
- 2025年55卷第10期 页码:106-113
收稿:2025-08-28,
纸质出版:2025-10-20
DOI: 10.7512/j.issn.1001-2303.2025.10.12
移动端阅览

浏览全部资源
扫码关注微信
收稿:2025-08-28,
纸质出版:2025-10-20
移动端阅览
VVER-1000堆型核电站主管道焊接是核岛安装工程的关键里程碑节点。主管道材料采用复合钢10ГН2МФА、15Х2НМФА-А(压力容器接管嘴),规格为
<math id="M1"><mi mathvariant="normal">⌀</mi></math>
https://html.publish.founderss.cn/rc-pub/api/common/picture?pictureId=92896489&type=
https://html.publish.founderss.cn/rc-pub/api/common/picture?pictureId=92896448&type=
2.53999996
2.03200006
990 mm×70 mm、
<math id="M2"><mi mathvariant="normal">⌀</mi></math>
https://html.publish.founderss.cn/rc-pub/api/common/picture?pictureId=92896490&type=
https://html.publish.founderss.cn/rc-pub/api/common/picture?pictureId=92896449&type=
2.53999996
2.03200006
1 000 mm×75 mm,材料属珠光体耐热钢,焊接与热处理工艺复杂、施工难度大。原“依次施工”方案存在存在工期长(约12个月)、作业环境恶劣、冷裂纹与收缩变形控制难等问题。通过分析母材焊接性,明确冷裂纹为重点防控对象,制定200 ℃预热、200~250 ℃后热(保温12 h)、620±20 ℃消应力热处理(保温6.5 h)等参数;优
化焊材(选用СВ-08Г2С等4类)、焊接方法(氩-电联合工艺)与坡口(双V形),经4项工艺评定验证可行性;将焊接顺序改为“平行法+搭接法”,配合变形监测与无损检验。后续应用表明,该工艺使主管道焊接一次合格率超96.8%,工期缩短约2个月,改善作业环境与安全性,属VVER堆型世界首创(已申请发明专利),对同类机组及其他堆型主管道焊接有指导与推广价值。
The welding of the main pipeline of VVER-1000 type nuclear power plant is a key milestone in the installation of the nuclear island. The main pipeline materials are made of composite steels 10ГН2МФА and 15Х2НМФА-А (vessel nozzles) with specifications of
<math id="M3"><mi mathvariant="normal">⌀</mi></math>
https://html.publish.founderss.cn/rc-pub/api/common/picture?pictureId=92896491&type=
https://html.publish.founderss.cn/rc-pub/api/common/picture?pictureId=92896464&type=
2.53999996
2.03200006
990 mm×70 mm and
<math id="M4"><mi mathvariant="normal">⌀</mi></math>
https://html.publish.founderss.cn/rc-pub/api/common/picture?pictureId=92896491&type=
https://html.publish.founderss.cn/rc-pub/api/common/picture?pictureId=92896464&type=
2.53999996
2.03200006
1000 mm×75 mm. The materials belong to pearlite heat-resistant steel
and the welding and heat treatment processes are complex
making the construction challenging. The original "sequential construction" plan had issues such as a long duration (about 12 months)
harsh working environment
and difficulties in controlling cold cracks and shrinkage deformation. By analyzing the weldability of the base metal
it was determined that cold cracks were the primary prevention target
. Parameters such as preheating at 200 ℃
post-heating at 200-250 ℃ (holding for 12 h)
and stress-relieving heat treatment at 620±20 ℃ (holding for 6.5 h) were established. The welding materials (selecting СВ-08Г2С and other 4 types)
welding methods (argon-electric combined technology)
and groove design (double V-shaped) were optimized. The feasibility was verified through four process evaluations. Innovatively
the welding sequence was changed to "parallel method + lap method"
combined with deformation monitoring and non-destructive testing. Subsequent applications showed that this process resulted in a primary qualification rate of over 96.8% for the main pipeline welding
shortened the construction period by about 2 months
improved the working environment and safety
and it is the world's first for VVER-type reactors (patent application has been filed). It has guiding and promoting value for similar units and other reactor main pipeline weldings.
徐井伟 , 马尚国 , 王丽思 , 等 . VVER-1000主管道焊接工艺性分析 [J]. 电焊机 , 2021 , 51 ( 2 ): 83 - 87 .
XU J W , MA S G , WANG L S . VVER-1000 Main Pipeline Welding Process Analysis [J]. Electric Welding Machine , 2021 , 51 ( 2 ): 83 - 87 .
刘斌 , 寇斌达 , 卢夏 , 等 . VER-1000机组主管道焊接接头冲击性能影响因素分析 [J]. 热力发电 , 2021 , 50 ( 7 ): 130 - 136
LIU B , KOU B D , LU X , et al . Analysis of Impact Performance Factors of VER-1000 Unit Main Pipeline Welded Joints [J]. Thermal Power Generation , 2021 , 50 ( 7 ): 130 - 136 .
陈祝年,焊接工程师手册 [M]. 北京 : 机械工业出版社 , 2010 .
中国机械工程学会 . 焊接手册 [M]. 北京 : 机械工业出版社 , 2001 .
田锡唐,焊接结构 [M]. 北京 : 机械工业出版社 , 1982 .
张文钺,焊接冶金学(基本原理) [M]. 北京 : 机械工业出版社 , 1995 .
才福胜 , SA 387 Gr11CL2和SA387Gr22CL2珠光体耐热钢的焊接 [J]. 石油化工设备 ,2011, 40 ( 6 ): 67 - 70 .
CAI F S . Welding of SA387Gr11CL2 and SA387Gr22CL2 Pearlitic Heat-resistant Steels [J]. Petroleum and Chemical Equipment , 2011 , 40 ( 6 ): 67 - 70 .
张建勋 , 薛承博 , 牛靖 , 等 . 核电厚壁管道全位置TIG焊动态焊接变形研究 [J]. 焊接 , 2009 ,2009( 11 ): 14 - 18 .
ZHANG J X , XUE C B , NIU J , et al . Research on Dynamic Welding Deformation of Thick-walled Pipes in Nuclear Power by Full Position TIG Welding [J]. Welding , 2009 , 2009 ( 11 ): 14 - 18
张佳浩 , 张颖 , 王鑫 , 等 . 一种高效预测厚壁管件焊接变形的有限元模拟方法 [J]. 压力容器 , 2017 , 34 ( 5 ): 46 - 57 .
ZHANG J H , ZHANG Y , WANG X , et al . A Highly Efficient Finite Element Simulation Method for Predicting Welding Deformation of Thick-walled Pipe Components [J]. Pressure Vessels , 2017 , 34 ( 5 ): 46 - 57 .
张艾丽 , 刘志斌 , 关伟宏 . 焊接件去应力退火工艺参数实验 [J]. 汽轮机技术 , 2000 , 42 ( 4 ): 251 - 253 .
ZHANG A L , LIU Z B , GUAN W H . Experimental Process Parameters of Stress Relief Annealing for Welded Parts [J]. Turbine Technology , 2000 , 42 ( 4 ): 251 - 253 .